The new development direction of decentralized wind power - market trading

the National Energy Administration Station issued the notice of the national development and Reform Commission and the National Energy Administration on carrying out the pilot of market-based trading of distributed generation (fgny [2017] No. 1901) on October 31, 2017, which clearly defined the project scale, market trading mode, and relevant policy support of distributed generation trading

for projects participating in the market-oriented transaction of distributed generation, if the machine meets the following requirements in the standby state: for projects with a voltage level of 35 kV and below, the unit capacity shall not exceed 20 MW (if there is its own power consumption, it shall not exceed 20 MW after deducting the maximum load of electricity consumption in that year). The capacity of the single project is more than 20 MW but not more than 50 MW, and the grounding voltage level is not more than 110 kV and is consumed nearby within the voltage level

take a 10 MW decentralized wind farm in Shandong Province as an example. When the static investment is 7800 yuan/kw and the full operating hours are 1800h, if the project is made into a market-based transaction, when seeking to ensure the income, it is conservatively estimated that the maximum electricity price discount can be provided for the user side

1. Determine subsidies

it is known that Shandong Province is a four class electricity price area. In 2018, the wind power tariff was 0.57 yuan/kwh, and the coal-fired benchmark electricity price in Shandong Province was 0.3949 yuan/kwh. It can be seen that the local kilowatt hour subsidy was 0.1751 yuan. The notice clearly states that for projects adopting the market transaction mode, the subsidy standard for wind power is determined by subtracting the benchmark electricity price of local wind power from the benchmark electricity price of coal-fired power (including desulfurization, denitration and dust removal electricity prices) and is moderately reduced. If the capacity of a single project does not exceed 20 MW of infrared radiation that can block the ambient temperature, the reduction in the demand for kilowatt hour subsidies shall not be less than 10%; If the capacity of a single project is more than 20 MW but not more than 50 MW, the reduction in the demand for kilowatt hour subsidies shall not be less than 20%. In addition, if the first graphene touch screen of the project will be listed within 35 years and the subsidy will be voluntarily abandoned, the capacity limit will be relaxed. Therefore, the maximum electricity subsidy for the project is 0.158 yuan, and the minimum electricity subsidy is more than 0 yuan

2. In the pilot project of market-oriented transaction of distributed generation, the "fee" is formulated by the provincial (District, city) price department in accordance with the relevant provisions of the national transmission and distribution electricity price reform, and reported to the national development and Reform Commission for the case of weak enterprise innovation ability. Before the verification of "fee passing", the transmission and distribution price of the highest voltage level involved in the market-oriented transaction of distributed generation will be deducted temporarily according to the provincial power transmission and distribution price (including policy cross subsidies) corresponding to the access voltage level of power users. The basic situation of the approved transmission and distribution electricity price in each province is shown in the figure below

3. Determine the range of sales electricity price

when the consumer side is 35kV, the electricity price is 0.6056 yuan/kwh. The particularity of this situation is that the voltage level at the user side is consistent with that at the transmission and distribution side. According to the current provisions of the notice on toll collection, theoretically, the toll collection is 0, and the specific charge standard is calculated according to the toll collection standard determined by the local electricity. In this example, it is temporarily calculated according to the charge of 0. It can be seen that the minimum sales price of the project is 0.6056 yuan/kwh (excluding subsidies), and the maximum is 0.6056+0.158=0.7636 yuan/kwh (including subsidies)

4. Determine the maximum electricity price discount that can be provided for the user side

on the premise of ensuring the internal rate of return of capital fund of 8%, the sales electricity price including value-added tax is calculated to be 0.531 yuan/kwh, 0.531/0.6056=87.68%, 0.531/0.7636=69.54%. Therefore, determine the maximum electricity price discount that can be provided for the user side according to the actual subsidies received. The specific transaction price depends on the availability of subsidies Determine the situation of competitors and negotiations with the user side